Project NameCentralized Wastewater Treatment Plant Project – Que Vo Industrial Park Expansion
Total Capacity:6,000 m³/day & night
Investor:Kinh Bac City Development Holding Corporation – JSC
Scope of Work:Supply of materials and equipment, installation, trial operation, operation training, technology transfer, and environmental permit application for the Wastewater Treatment Plant – Capacity: 6,000 m³/day & night. Effluent quality meets QCVN 40:2011/BTNMT standard.
Location:Que Vo Industrial Park Expansion, Que Vo District, Bac Ninh Province
Implementation Period:2022–2023
Progress:Completed